Project Overview
Installation of new 12 kV utility service, 12 kV – 480 transformer, 480 volt switchgear, two 1.5 MW emergency generators, automatic transfer switchgear and interconnection to existing hospital main electrical equipment requiring 24/7 operation. The project includes motor control centers serving mechanical equipment.
Project Details
Completed: 2015
Owner: Kaiser Foundation Hospitals
Architect: HY Architects
Services Provided:
- Electrical Distribution
- Lighting Design